Good day. This is the April 17 report report. We will be publishing for the Community of Allenstown School District a weekly progress report ofyournew building project. We plan to publish these reports on every Monday going forward.
Good morning. The entire construction team of Turner Group, Milestone Construction and Gordon Bristol Consulting wishes to extend our sincere sympathy to the family of Mr. Peter Warburton the Superintendent of Schools for the Allenstown District on his passing.
Peter was dedicated beyond belief in your construction project and was instrumental in putting together the best team possible to ensure a quality and long lasting building for the student, staff and citizens of the Allenstown area.
His passing strikes us all.
________
Current work efforts.
Your OPM and Milestone performed a safety review of site observations last week. The site is clean, safe and being operated according to good construction site practices.
Your site engineer and OPM conducted a table top exercise of the State of New Hampshire Fish and Wildlife procedures to be used during the construction phase of this project. The table top exercise was a success and we have filed our first bi-weekly report to the State on your behalf regarding our F&W observations.
__________
Interior metal framing continues
Exterior metal framing continues
Plumbing under slab complete
Sprinkler work commenced
Site work continues about 60% finished
We have an average of 80 workers a day on site
Masons have commenced work.
Roofing is ongoing.
Fire Pump building arrives this week
Only two concrete pours for flooring remain. A classroom area on first floor and the sub floor for the gymnasium floor.
We are continuing to look at owner fit-up items such as security, cameras, door access.
Overall the schedule is on time and on budget.
Also, please feel free to call me at 802-380-1157 or write me at[email protected]