As we enter the middle of March 2023 we are still confident to state that we are ON TIME and ON BUDGET.
At this time the steel frame of the building is 100 percent complete.
Exterior framing of the building has commenced. When you drive by you can begin to see the outline of the doors and windows throughout the building.
Concrete floors have been poured in 75% of the building.
All underground piping within the building is complete.
Work on the final roof for the building is about 50% complete.
As an aside, we have the building steel independently tested for our files. We do not just rely upon the contractor but the school hires independent testing.
At the current time the septic system is approximately 85% complete.
On the financial front. Amber and Gordon are doing a true-up of the budget this week. However, my draft notes show that we are on budget just about to the penny. Between the General Contract with Milestone and the owner items we appear to have committed about $32,332,000 of the 32,350,000. However, I want to vet those numbers with Amber but want to give you my best educated calculation at this time.
The administration will be talking to the Board about possible spending of school line items but the construction budget remains in excellent shape at this time. Also at this time we have spent approximately $11,000,000 of the $28,000,000 allowed to Milestone. So we are well underway.