On Monday, May 16th, the Allenstown School Board hosted a New School Community Forum to give Allenstown residents a chance to see the new school building drawing designs and site layout.  The forum was facilitated by the Owner's Project Manager, Gordon Bristol; with presentations by Doug Proctor, the principal architect; and Erin Lambert, the civil engineer for the site.  Mr. Bristol closed the forum out with the reminder to all that he does have project updates on the new school website and to feel free to email him, or the Allenstown School Board with any questions that arise regarding the new school project.

Allenstown Community School Update

Welcome and thank you for visiting the NEW K-8 school progress web page. We will keep this section up to date with the latest renderings, information, and historical data.

August 7th, 2023 Update

Good day.  This is the August 7 report report.  We will be  publishing for the Community of Allenstown School District a weekly progress report of your new building project.  We plan to publish these reports on every Monday going forward.

Current work efforts.

__________

We are transitioning to our final finishes on the building.  The building is erected.  99% of the internal infrastructure is complete.  HVAC and electrical and plumbing for rough install.

We now begin the "finishing touches”

Masonry siding is well underway.  Looking GREAT!!!

Mechanical work continues with the installing of final duct work within the building.

Electrical work continues.   In particular we are working on the switch gear room.  This is where the main electrical comes into the building from the utility.

Roof is completed..

Insulated metal panels for exterior of building is ongoing.

Drywall work interior continues. The second floor drywall is 80% complete.  Work on the 1st floor drywall commences this week.

We have started some painting in the interior.  (Minimal but a start)

Windows continue to be installed.

Project remains 100% on time for a March 2024 handover.

Project remains on budget!!!

Also, please feel free to call me at 802-380-1157 or write me at[email protected]

Wildlife Assessment

"All of our site plans are fully reviewed by a number of New Hampshire state agencies.  We have not had any mention of eagle disturbance during any of our conversations with the State.  We feel comfortable that there are no eagle issues as we have vetted your plans widely”.  Erin Lambert, PE, LEED AP, Wilcox & Barton, Inc.